Kinetic LED Installation and Commissioning Guide
Kinetic LED installation is a mechanical, structural, electrical and control-system task at the same time. The supporting structure must carry the static display and the effects of repeated movement; the installation must also preserve the full motion envelope, service access, cable routes and safe shutdown functions.
A reliable commissioning sequence starts with the structure and one motion unit, then expands to rows or groups, full trajectories and finally synchronized LED playback.

Check the Supporting Structure Before the Screen
JYVISIONS installation practice starts with structural load and geometry rather than LED alignment. The support must be checked for the intended kinetic system and its dynamic behavior. Internal engineering guidance uses a dynamic factor of 1.5 and calls for modal analysis where structural resonance is a concern; these are JYVISIONS engineering rules, not universal building-code values.
The installation manual covers floor-supported, floor + wall, floor + ceiling and wall-hanging approaches. The correct method depends on the project structure and movement direction.

Reserve the Full Motion Envelope
Do not design from the static screen depth alone. Stroke, moving geometry, service access and safe clearance must all fit inside the available space. This is especially important for rotating layers and telescopic spheres, where the moving envelope can extend beyond the apparent static footprint.
For rotating systems, see the 360° rotating LED screen before freezing the movement envelope. For radial expansion, see the kinetic LED sphere before confirming structural clearance.
Alignment and Flatness Affect Motion Quality
The supporting surface should be checked with appropriate leveling tools before the kinetic units are commissioned. JYVISIONS internal installation guidance uses a flatness target of no more than 2 mm per meter for the relevant telescopic system. Treat this as a project engineering requirement from JYVISIONS, not as an industry-wide standard.
Separate Power and Communication Routes
Power and shielded communication cables should be routed to reduce interference and to remain serviceable throughout the movement range. JYVISIONS internal guidance calls for approximately 30 cm separation between power and shielded communication routes where practical, and single-point grounding of the CAN shield in the applicable CAN architecture. Exact routing must still follow the project electrical design and local requirements.

Commission From One Unit to the Full System
JYVISIONS commissioning practice is staged: first jog and verify a single module, then confirm row or group synchronization, preview the intended trajectory, and only then verify synchronization with LED playback. This makes it easier to isolate mechanical, communication and content-timing problems before they become system-wide faults.
Verify Limits, Emergency Stop and Communication-Loss Behavior
The JYVISIONS telescopic control architecture uses layered protection including software limits, electronic proximity limits and a mechanical hard stop. Emergency stop is designed as a hardwired function that cuts motor power independently of normal CAN communication and requires manual reset. Communication-loss and stall-current protections are also part of the engineering logic.
These are first-party architecture details, not an independent safety certification. The final installation must still comply with the project’s applicable safety and electrical requirements.

Complete Commissioning Before Handover
Before handover, verify the full motion trajectory, movement clearances, limits, emergency stop, communication stability, LED-motion synchronization and service access. Record the accepted configuration so later maintenance does not depend on memory.